2015 Build Dates Set
22 September 2014
Mason Care-A-Vanner builds for 2015 have been scheduled and submitted to Americus for posting. They go live for sign-up on Monday 29 September at 11:30 am Eastern. The link for Care-A-Vanner information and signup is http://www.habitat.org/rv/
Phase 1: 8 to 22 February 2015, 11 rigs. Framing on two adjacent new homes.
Phase 2: 22 February to 15 March, 11 rigs. Continue framing to dried in on two homes.
Phase 3: 15 to 29 March, 11 rigs. Subs doing insulation and dry wall while we finish exteriors and interior when we can get in.
Phase 4: 29 March to 19 April, 11 rigs. Two homes to completion and dedication.